Guest wrote:What is actually inspected? What would fail in a 5yr but not stop the vessel from sailing the previous season or seasons?
Here is a link to the official ABS guide for Survey Rules After Construction. It makes for some (not-so) light bedtime reading...
https://ww2.eagle.org/content/dam/eagle ... -nov07.pdf
Many items are left up to discretion of the attending Surveyor. In my experience managing shipyard periods for new vessels (<5 years old), the Surveyors were quite lenient and casually glanced at most items on the list, occasionally finding an issue that merited further discussion. Likewise, while managing the drydocking of a tanker with 15+ years, the Surveyors came aboard in their blue boiler suits, intending to dig into the nooks and crannies of the ship. Hull gauging (measuring the thickness of the steel), weldment integrity, and general plate distortion were a much higher priority. Safety systems were also checked more thoroughly. Many pieces of the survey were actually done prior to arrival at the shipyard, for instance, rafting cargo tanks to gauge plate and frame thickness and overall condition (slowly filled a cargo tank with water and an inflatable raft held two people who paddled around with their ultrasonic measurement tools).
Machinery is also inspected. Certain pieces of machinery must be disassembled and checked once every 5 years. Skin valves - the valves isolating the sea from interior piping - are removed and overhauled. The propellor(s) is removed and the tailshaft is withdrawn and measured for wear. Generally, new stern tube seals are installed at this time. The propellor will be machined if any damage is observed.
The actual time required in the drydock is only a few days if all goes well, and no major plate renewal is required. A majority of the survey can be conducted whilst the vessel is in the water, moored to a dock. Modern technology also greatly speeds up the process. Now, a diver, or remote operated vehicle, can check the underwater portion of the hull before arriving at the shipyard, reducing the likelihood of surprises once the drydock is pumped out.
Since some items are only thoroughly checked once every shipyard period, it is very possible that a problem exists, but only found when the ship and systems are gone over more in-depth in drydock. Depending on what issue is found - say steel corrosion - a ship could be sailing as normal, but then put to a stop once the drydocking shows the true condition. This has been the root cause of the demise of some Great Lakes ships in recent times...a ship trades as usual, with the company knowing the next drydocking will be expensive due to repairs needed, thus ending the career of the ship.
[quote="Guest"]What is actually inspected? What would fail in a 5yr but not stop the vessel from sailing the previous season or seasons?[/quote]
Here is a link to the official ABS guide for Survey Rules After Construction. It makes for some (not-so) light bedtime reading...
https://ww2.eagle.org/content/dam/eagle/rules-and-guides/archives/conventional_ocean_service/2_steelvesselrules2007/part_7_e-nov07.pdf
Many items are left up to discretion of the attending Surveyor. In my experience managing shipyard periods for new vessels (<5 years old), the Surveyors were quite lenient and casually glanced at most items on the list, occasionally finding an issue that merited further discussion. Likewise, while managing the drydocking of a tanker with 15+ years, the Surveyors came aboard in their blue boiler suits, intending to dig into the nooks and crannies of the ship. Hull gauging (measuring the thickness of the steel), weldment integrity, and general plate distortion were a much higher priority. Safety systems were also checked more thoroughly. Many pieces of the survey were actually done prior to arrival at the shipyard, for instance, rafting cargo tanks to gauge plate and frame thickness and overall condition (slowly filled a cargo tank with water and an inflatable raft held two people who paddled around with their ultrasonic measurement tools).
Machinery is also inspected. Certain pieces of machinery must be disassembled and checked once every 5 years. Skin valves - the valves isolating the sea from interior piping - are removed and overhauled. The propellor(s) is removed and the tailshaft is withdrawn and measured for wear. Generally, new stern tube seals are installed at this time. The propellor will be machined if any damage is observed.
The actual time required in the drydock is only a few days if all goes well, and no major plate renewal is required. A majority of the survey can be conducted whilst the vessel is in the water, moored to a dock. Modern technology also greatly speeds up the process. Now, a diver, or remote operated vehicle, can check the underwater portion of the hull before arriving at the shipyard, reducing the likelihood of surprises once the drydock is pumped out.
Since some items are only thoroughly checked once every shipyard period, it is very possible that a problem exists, but only found when the ship and systems are gone over more in-depth in drydock. Depending on what issue is found - say steel corrosion - a ship could be sailing as normal, but then put to a stop once the drydocking shows the true condition. This has been the root cause of the demise of some Great Lakes ships in recent times...a ship trades as usual, with the company knowing the next drydocking will be expensive due to repairs needed, thus ending the career of the ship.